During the last couple of weeks, we’ve been working hard on a big project that is soon coming to its finale. Our crews have busy constructing a new Starbucks in the Boston area. We’re very happy with the progress of this project and are excited that it is approaching its finish.
We’ve already completed several inspections, including rough plumbing and electrical, followed by framing inspection, ceiling grid and fire system inspections. Electrical and plumbing inspections were also completed on time.
The JDC team and its trusted subcontractors have finished flooring and tiling, and are currently working on casework and equipment installation, as well as lighting fixtures, all electrical work and plumbing fixtures. The final steps toward opening the new Starbucks store include painting, artwork installation, new furniture lay-out, and a final inspection.